Tasks are critical if slack is less than or equal to

Specifies the number of days of slack Project uses to determine critical tasks.

If you enable this setting, tasks are marked as critical if the slack is less than or equal to the value you specified.

If you disable or do not configure this setting, the user's default setting is used.

Supported on: At least Windows Vista

Tasks are critical if slack is less than or equal to

Registry HiveHKEY_CURRENT_USER
Registry PathSoftware\Policies\Microsoft\Office\12.0\MS Project\Options\Calculation
Value NameShow As Critical if Slack
Value TypeREG_DWORD
Default Value0
Min Value0
Max Value9999