Move end of completed parts after status date back to status date

Moves the completed portion of a task back to finish at the status date.

If you enable this setting, the completed portion of the task moves back to finish at the status date.

If you disable or do not configure this setting, the user's default setting is used.

Supported on: At least Windows Vista

Registry HiveHKEY_CURRENT_USER
Registry PathSoftware\Policies\Microsoft\Office\12.0\MS Project\Options\Calculation
Value NameMoveCompleted
Value TypeREG_DWORD
Enabled Value1
Disabled Value0

proj12.admx

Administrative Templates (Computers)