Days per month

Defines the number of days that you want Project to assign to a task when you enter a duration of a month.

If you enable this setting, month-long tasks will be assigned the number of days that you specified.

If you disable or do not configure this setting, the user's default setting is used.

Supported on: At least Windows Vista

Days per month

Registry HiveHKEY_CURRENT_USER
Registry PathSoftware\Policies\Microsoft\Office\12.0\MS Project\Options\Calendar
Value NameDefault Days/Month
Value TypeREG_DWORD
Default Value20
Min Value0
Max Value100

proj12.admx

Administrative Templates (Computers)

Administrative Templates (Users)