New tasks are effort driven

Specifies that new tasks are scheduled such that the work on the task remains constant as you add or remove assignments.

If you enable this setting, new tasks will be effort-driven.

If you disable or do not configure this setting, the user's default setting is used.

Supported on: At least Windows Vista

Registry HiveHKEY_CURRENT_USER
Registry PathSoftware\Policies\Microsoft\Office\12.0\MS Project\Options\Scheduling
Value NameNew Tasks Effort Driven
Value TypeREG_DWORD
Enabled Value1
Disabled Value0