Specifies the day of the week on which you want the scheduling week to begin.
If you enable this setting, weeks will start on the day you specified.
If you disable or do not configure this setting, the user's default setting is used.
Registry Hive | HKEY_CURRENT_USER |
Registry Path | Software\Policies\Microsoft\Office\12.0\MS Project\Options\Calendar |
Value Name | Start Week Day |
Value Type | REG_DWORD |
Value | 6 |
Registry Hive | HKEY_CURRENT_USER |
Registry Path | Software\Policies\Microsoft\Office\12.0\MS Project\Options\Calendar |
Value Name | Start Week Day |
Value Type | REG_DWORD |
Value | 0 |
Registry Hive | HKEY_CURRENT_USER |
Registry Path | Software\Policies\Microsoft\Office\12.0\MS Project\Options\Calendar |
Value Name | Start Week Day |
Value Type | REG_DWORD |
Value | 1 |
Registry Hive | HKEY_CURRENT_USER |
Registry Path | Software\Policies\Microsoft\Office\12.0\MS Project\Options\Calendar |
Value Name | Start Week Day |
Value Type | REG_DWORD |
Value | 2 |
Registry Hive | HKEY_CURRENT_USER |
Registry Path | Software\Policies\Microsoft\Office\12.0\MS Project\Options\Calendar |
Value Name | Start Week Day |
Value Type | REG_DWORD |
Value | 3 |
Registry Hive | HKEY_CURRENT_USER |
Registry Path | Software\Policies\Microsoft\Office\12.0\MS Project\Options\Calendar |
Value Name | Start Week Day |
Value Type | REG_DWORD |
Value | 4 |
Registry Hive | HKEY_CURRENT_USER |
Registry Path | Software\Policies\Microsoft\Office\12.0\MS Project\Options\Calendar |
Value Name | Start Week Day |
Value Type | REG_DWORD |
Value | 5 |