Resource Assigments

Specifies that the feedback triangle should appear in a corner of a field if the user assigns additional resources to a task that already has resources assigned.

If you enable this setting, a feedback triangle is displayed in the corner of a field if users assign additional resources to a task that already has resources assigned.

If you disable or do not configure this setting, the user's default setting is used.

Supported on: At least Windows Vista

Registry HiveHKEY_CURRENT_USER
Registry PathSoftware\Policies\Microsoft\Office\12.0\MS Project\Options\Interface
Value NameResourceAssignOOUI
Value TypeREG_DWORD
Enabled Value1
Disabled Value0

proj12.admx

Administrative Templates (Computers)

Administrative Templates (Users)