Hours per week

Specifies the number of hours that you want Project to assign to a task when the user enters a duration of one week.

If you enable this setting, week-long tasks will be assigned the number of hours that you specified.

If you disable or do not configure this setting, the user's default setting is used.

Supported on: At least Windows 7

Hours per week

Registry HiveHKEY_CURRENT_USER
Registry Pathsoftware\policies\microsoft\office\16.0\ms project\options\calendar
Value Namedefault hours/week
Value TypeREG_SZ
Default Value40