And move end of completed parts forward to status date

Moves the completed portion of a task forward to finish at the status date.

If you enable this setting, the completed portion of the task moves forward to finish at the status date.

If you disable or do not configure this setting, the user's default setting is used.

Supported on: At least Windows 7

Registry HiveHKEY_CURRENT_USER
Registry Pathsoftware\policies\microsoft\office\16.0\ms project\options\calculation
Value Nameandmovecompleted
Value TypeREG_DWORD
Enabled Value1
Disabled Value0