Specifies that all new tasks have estimated durations.
If you enable this setting, all new tasks will require estimated durations.
If you disable or do not configure this setting, the user's default setting is used.
Registry Hive | HKEY_CURRENT_USER |
Registry Path | software\policies\microsoft\office\14.0\ms project\options\scheduling |
Value Name | new tasks have estimated durations |
Value Type | REG_DWORD |
Enabled Value | 1 |